650 Broadway
Manhattan, NY 10012BBL 1-00529-0004Map
Owner of record: 650 Realty, INC.
650 Broadway is an office building built in 1860 in Manhattan, 10012. The owner of record is 650 Realty, INC.. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 61
- ECB violations
- 76
- HPD complaints
- 3
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 61
- Low pressure boiler boiler required
Violation issued-failure to file 2024 external low pressure inspection
Nov 14, 2025
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 20, 2021
Dob violation - resolved - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 28, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 28, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 30, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 2, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 2, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jan 9, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Dec 11, 2019
Dob violation - dismissed
Show 40 more ↓
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 27, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 27, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 13, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 4, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 4, 2019
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 19, 2018
Dob violation - resolved - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2016 inspection report
Apr 6, 2018
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 11, 2017
Dob violation - resolved - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2015 inspection report
Feb 24, 2017
Dob violation - active - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 1, 2016
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Mar 21, 2016
Dob violation - resolved - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 7, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 7, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
May 13, 2015
Dob violation - dismissed - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2012 inspection/test
Mar 31, 2014
Dob violation - active - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jan 15, 2014
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jan 15, 2014
Dob violation - dismissed - Landmark none
Landmk-landmark none
Apr 30, 2013
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Oct 15, 2012
Dob violation - resolved - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2011 inspection/test
Oct 1, 2012
Dob violation - active - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2010 inspection/test
Dec 13, 2011
Dob violation - active - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jan 13, 2011
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Jan 5, 2011
Dob violation - resolved - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Dec 2, 2010
Dob violation - dismissed - Landmark none
Landmk-landmark none
Nov 18, 2010
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Mar 30, 2010
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Mar 30, 2010
Dob violation - resolved - Low pressure boiler boiler required
Lblvio-low pressure boiler boiler required
Dec 31, 2009
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
May 6, 2009
Dob violation - resolved - Elevator elevatoroptional
Ll1081-local law 10/81 - elevator elevatoroptional
Feb 27, 2009
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Nov 13, 2007
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Mar 8, 2007
Dob violation - resolved - Landmark none
Landmk-landmark none
Jul 20, 2006
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
May 18, 2006
Dob violation - resolved - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jan 6, 2006
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Aug 10, 2005
Dob violation - resolved - Elevator elevatoroptional
Ll1081-local law 10/81 - elevator elevatoroptional
Nov 19, 2004
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Oct 8, 2004
Dob violation - resolved - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 13, 2004
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Dec 23, 2003
Dob violation - resolved
ECB violations · 76
- Class - 2
Failure to comply with the commissioner's order to file a certificate of correction with the department of buildings.no certificate of correction for vio#39101572l as of 10/21/25. for defacing stop work order s
Oct 21, 2025 · Penalty $6,250
Active - Class - 1
Unlawful acts: failure to comply with commissioner's order and file a certificate of correction pursuant to 28-2-1.1 and rcny 102-01. i observed in dob records the improper permit submitted in regards to ecb# 3
May 13, 2024 · Penalty $12,500
Active - Class - 1
Unlawful acts: failure to comply with commissioner's order as stated in ecb #39026404p issued on 08/05/2020 and file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01., comply with commissioner'
Feb 9, 2024 · Penalty $12,500
Active - Class - 1
Unlawful acts: failure to comply with commissioner's orders as stated in ecb #39026397x issued on 08/05/2020 and file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01., comply with commissioner
Feb 9, 2024 · Penalty $6,250
Resolve - Class - 1
Stop work order removed, comply with code
Dec 15, 2023 · Penalty $2,530
Active - Class - 1
Unlawful acts: failure to comply with the commissioners order contained in summons/violation# 39026404p issued on 08/05/2020 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01., compl
Dec 13, 2023 · Penalty $2,530
Active - Class - 1
Unlawful acts: failure to comply with the commissioners order contained in summons/violation# 39026397x issued on 08/05/2020 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01., compl
Dec 13, 2023 · Penalty $2,530
Resolve - Class - 2
Failure to comply w/the comm's order contained in summons/vio#39009301h issued on 09/11/19 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01(d)(2). an acceptible certificate has not yet been fi
Sep 28, 2020 · Penalty $1,250
Resolve - Class - 2
Steam equalizer is leaking-hw re circulator at aosmith hwh is defective-boiler safety discharge pipe is reduced-gas meter area has no ventilation; correct violation and submit the certificate of correction
Sep 15, 2020 · Penalty $625
Active - Class - 2
Failure to maintain building code compliant manner noted observed facade metal in slate of disrepair at roof cornice level and second floor level (cracked and rusted) repair or replace
Sep 15, 2020 · Penalty $625
Active
Show 40 more ↓
- Class - 2
Failure to comply w/ the commissioner's order contained in summons/vio#35433323x issued on 7/8/2020 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. failure to promptly notify the
Sep 15, 2020 · Penalty $1,250
Resolve - Class - 1
New piping, valves, and fixtures installed in 4th floor commercial space without securing requisite permits., obtain permit
Aug 5, 2020 · Penalty $1,250
Active - Class - 1
New electric switches, receptacles, conduits, fittings, junction boxes, and panels installed in 4th floor commercial space without requisite permit., obtain permit
Aug 5, 2020 · Penalty $400
Resolve - Class - 1
Premises 5-story attached mixed use building.observed front facade ornamental metal in state of disrepair.condition in various locations,including both corner of roof cornice cracks&loose sheet metal.ornamental
Jul 8, 2020 · Penalty $3,125
Active - Class - 2
Failure to comply with the commissioner's order to file certificate of correction: noted: previous ecb violation #35249876x was issued on 01/12/2018 for occupancy contrary to c of o. hearing date for violation
Mar 26, 2020 · Penalty $1,250
Resolve - Class - 1
No door lock monitoring installed in this controller as mandated by 3.10.12 of appendix k.3 of the 2014 nycbc this is a controller feature which ensures passengers safety remedy file application install dlm and
Mar 13, 2020 · Penalty $1,250
Active - Class - 1
No doorlock monitoring installed in this controller as mandated by 3.10.12 of appendix k3 of the 2014 nycbc. this is a feature that ensures passenger safety. replace worn door and gate gibbs. provide means of a
Jan 16, 2020 · Penalty $1,250
Active - Class - 2
Occupancy contrary to that allowed by the certificate of occupancy or buildings dept records dob records co #112561 indicates 2nd floor 95 photo processing use group 6.illegal occupancy noted:2nd floor occupied
Jan 9, 2020 · Penalty $1,250
Active - Class - 2
Failure to comply with commissioners orders to file certificate of correction with department of buildings for violation #35373354r, file a certificate of correction
Dec 5, 2019 · Penalty $6,250
Resolve - Class - 2
Failure to maintain building in code compliant manner at rear of building at first floor fire escape basket has missing/damaged metal slats.remedy: repair replace
Nov 29, 2019 · Penalty $625
Resolve - Class - 2
Flue for hot water heater piped incorrectly-cover for pressure switch missing-discharge piping for safety valve reduced-insulation from steam piping missing ; correct all violating conditions submit a certifica
Nov 25, 2019
Resolve - Class - 1
Failure to maintain bldg in code compliant manner. noted at rear facade exp#3 metal shutters rusted out & not security attached to bldg facade throughout also fire excape basket broken &/or missing metal sluds
Oct 18, 2019 · Penalty $3,125
Active - Class - 2
Failure to comply w/the comm's order contained in summons/vio#39008935p issued on 09-05-18 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. failure to provide unobstructed exit passageway. no c of c on
Oct 10, 2019 · Penalty $1,250
Resolve - Class - 2
Failure to maintain bldg in code compliant manner. note: at exp#1 at all floors decorative cornice molding in disrepair w/cracked & spalling concrete throughout sidewalk shed installed under permit#m00163409
Oct 10, 2019 · Penalty $625
Active - Class - 1
As per one, ao smith gas fired hw heater. built date 03/2018. work w/o a permit ; apply for proper permits correct all violating conditions and call for an inspection., obtain permit
Sep 11, 2019 · Penalty $2,530
Active - Class - 2
Flue piping for hot water heater installed incorrectly.
Sep 11, 2019 · Penalty $625
Active - Class - 1
Failure to maintain building facade in code compliant manner. observed disrepair, deteriorated and cracks on ornamental facade metal and cornice at expo # 01 and metal shutters rusted out and not securely conne
Sep 5, 2019 · Penalty $1,250
Active - Class - 1
Failure to provide unobstructed exit passageway. observed fire escape in rear yard partially obstructed by metal window shutters at 2nd to 5th floor level. metal shutters are not attached to the building and ob
Sep 5, 2019 · Penalty $1,250
Active - Class - 1
Failure to maintain bldg walls/appurtenances. noted: at rear facade exp#3 metal shutters rusted out & not securely connected to bldg facade throughout also noted fire escape basket broken &/or missing metal
Aug 14, 2019 · Penalty $6,250
Active - Class - 2
5e1,10h11,16j1,17h11,29l10,40p16. 5e1-car door rubbing adjust;10h11 car door gibs worn replace; 16j1-hoistway door misaligned adjust; 17 h1-hoistway door gibs worn repalce; 29l10-door hanger defective repair
Jul 24, 2019 · Penalty $655
Resolve - Class - 2
Flue pipe for water heater not piped correctly-pressure relief valve for water heater not piped down. correct all violating conditions and submit a certificate of correction.
Jun 10, 2019 · Penalty $625
Active - Class - 1
As per one ao smith water heater. model# bt-80 400. serial# 1810109561259. built date 03/08/2018. work w/o a permit. apply for proper permits, correct all violating conditions and call for an inspection., obtai
Jun 10, 2019 · Penalty $1,250
Active - Class - 1
Observed disrepair, damaged and open metal gates in entire rear facade at expo # 03 over the alley way in between 2-buildings. alley use for car park and emergency exits. also observed disrepair front facade de
Jun 6, 2019 · Penalty $3,125
Active - Class - 2
15i11,57b11,59bb5,56y10. 16i11-worn and damaged a hoistway door release rollers repalce; 57b11-fire extinguisher has lost charge nad expired tag repalce; 59bb5-expired brake tag; perform and file test in logbo
May 14, 2019
Resolve - Class - 1
6a10 car door restrictor missing parts repair or replace.
Mar 13, 2019
Resolve - Class - 2
Occupancy contrary to that allowed by the certificate of occupancy or building departments records.at time of inspection i noted 3 floors being used as business contrary to cofo #112561.the 4th floor is being u
Feb 5, 2019 · Penalty $1,250
Active - Class - 2
Bc28-118.3.altered/changed building occupied without a valid cofo as per 28-118.3.1-28-118.3.2.at time of inspection i noted 3 floors that were altered had been occupied under job 1025890 without a valid cofo i
Feb 5, 2019
Resolve - Class - 2
Failure to comply w/the comm's order to file a cert of correction w/the dob. noted: premises 5 sty attached nfp masonry frame bldg. vio#35197463x issued on 8-24-16 for at front facade(exp#1)metal sills & cornic
Jan 30, 2019 · Penalty $1,250
Resolve - Class - 2
Failure to comply with commissioner's order contained in summons/violation #32091252l issued on 7/31/17, and to file a certificate of correction pursuant to 28.201.1 and 1rcny 102-01(d)(2). an acceptable certif
Apr 9, 2018 · Penalty $1,250
Resolve - Class - 3
Failure to maintain bldg in code compliant manner. noted: at front facade,point is peeling from cast iron elements also some rusting happening on facade ports. remedy: repair &/or replace.
Feb 8, 2018
Resolve - Class - 2
Failure to comply with the commissioners order to file a certificate of correction with the departmeant of building for violation#35167004j,issued on 06/23/16.rem:file a certificate of correction.
Feb 3, 2018 · Penalty $800
Resolve - Class - 3
Occupancy contrary to that allowed by the certificate of occupancy or building dept recors. noted: from second floor through fifth floor contrary to certificate of occupancy. second floor is a martial arts stud
Jan 12, 2018 · Penalty $400
Active - Class - 2
B254,36,50,50a,50b.50 holes in room-seal holes.50a open electric boxesseal boxes.50b discharge on relief-install discharge pile.50c piping not support-support piping.found weil mclain gas steam boiler unregiste
Jul 31, 2017 · Penalty $500
Active - Class - 2
Failure to maintain bldg walls or appurtenances. noted: at the time ofmy inspection,at front facade metal sills at 2nd,3rd,4th & 5th floors are in a state of disrepair w/coroded metal at various locations. meta
Aug 24, 2016 · Penalty $1,250
Active - Class - 2
Occupancy contrary to that allowed by the certificate of occupancy on bldg dept records.noted as per certificate of occupancy #112561 issueddate 04-29-1997 indicate 2nd flr a photo processing and 3rd flr a manu
Jun 23, 2016 · Penalty $1,200
Active - Class - 2
Failure to maintain bldg wall or appurtenances.at front facade metal sills at 2nd, 3rd, 4th and 5th floors in state of disrepair with corroded metal at various locations.also metal cornice rotted and in state
Apr 14, 2016 · Penalty $250
Active - Class - 2
59u15,68b07,61l10,39l10,10j01. no tag stating date of brake maintenance no entry of date of brake maintenance in log,main line box locking device is insufficient,outrigger on top of car is loose and bent,car
Mar 28, 2016
Resolve - Class - 1
B154,51. 51-cease use weil mclain 580 boiler and ao smith ptc230 hot water heater. draft inducer installed incorrectly and not working. do not operate boiler until all hazardous conditionhs are immediately cor
Mar 9, 2016 · Penalty $1,000
Active - Class - 2
02b10,56y10,68b07,68m07,59m07,100x10. 02b10-outside communication not working properly must repair; 56y10-hoist machine with oil leak must repair; 68b07-maintenance log provide up to date; 68m07-mcp missing pr
Feb 23, 2016
Resolve - Class - 2
02l10,60b07. 02l10-outside communication not working properly-repair 60b07-only 2 low wattage light bulb in motor room,provide better lighting.
Nov 27, 2015
Resolve
Complaints
- Unsanitary condition
Garbage/recycling storage
Aug 21, 2014 · Apt BLDG
Close - Electric
No lighting
Aug 21, 2014 · Apt BLDG
Close - Electric
No lighting
Aug 21, 2014 · Apt BLDG
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Office building (O5)
- Year built
- 1860
- Floors
- 5
- Residential units
- —
- Building area
- 18,850 ft²
- Lot area
- 3,770 ft²
- Zoning
- M1-5/R9A
- Community board
- 102
- Council district
- 2
- Block / lot
- 529 / 4
- Assessed value
- $2,548,800
- Landmark / historic district
- NoHo Historic District
Questions about 650 Broadway
Who owns 650 Broadway?
The owner of record in NYC Department of City Planning PLUTO data is 650 Realty, INC..
Does 650 Broadway have violations?
NYC HPD has no housing violations on record for this property.
Is 650 Broadway rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 650 Broadway built?
City records list 1860 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.