roofy

63 Crosby Street

Manhattan, NY 10012BBL 1-00482-0013Map

Owner of record: 61 Crosby Owner LLC

63 Crosby Street is an office building built in 1900 in Manhattan, 10012. The owner of record is 61 Crosby Owner LLC. HPD has recorded 4 housing violations here, most recently on April 16, 2021.

HPD violations
4
DOB violations
13
ECB violations
10
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Apr 16, 2021

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 4

  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 16, 2021

    Closed — Violation closed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Apr 16, 2021

    Closed — Violation closed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Dec 6, 2017

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 23, 2016

    Closed — Violation dismissed

DOB building violations · 13

  • Low pressure boiler boiler required

    Violation issued-failure to file 2018 external low pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2019 external low pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Nov 8, 2019

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Oct 11, 2017

    Vp*-violation unserved ecb- dismissed
  • Construction other optional

    C-construction other optional

    Oct 11, 2017

    Vp*-violation unserved ecb- dismissed
  • Construction other optional

    C-construction other optional

    Oct 11, 2017

    Vp*-violation unserved ecb- dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2012 inspection report

    May 15, 2014

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Feb 10, 1997

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Aug 29, 1995

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Mar 7, 1995

    Vp-violation unserved ecb-active
Show 3 more ↓
  • Construction other optional

    C-construction other optional

    Mar 7, 1995

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Mar 18, 1994

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Mar 18, 1993

    Dob violation - dismissed

ECB violations · 10

  • Class - 2

    Temporary construction equipment on site w/expd permit.note:at time of inspection observed supported scaffold in place w/permit no longer valid which ecpd on 8/1/17.rem:renew permit.comply w/code.

    Oct 27, 2017 · Penalty $400

    Resolve
  • Class - 1

    Sec. 3309.14 failure to protect skylight. at time of inspection i observed skylight at exp#4 unprotected,skylights from cmu mansonry operations. remedy: provide protection of sky lights as per code.

    Oct 11, 2017 · Penalty $1,600

    Resolve
  • Class - 1

    Designation of consktruction superintendent. note: at time of inspection of a 5 sty nb at 4th fl construction in progress. upon request of the construction superindent for construction operations,a labor said h

    Oct 11, 2017

    Resolve
  • Class - 2

    Sec. 3307.2.1 failure to comply w/dot regulations. at time of inspection of a 5 sty alt-1 at 4th fl i observed cmu palets stacked 2 high approx 8feet bags of cement & bricks stored on the street w/no dot permit

    Oct 11, 2017 · Penalty $400

    Resolve
  • Class - 1

    Failure to maintain documents on site required by chapter 33,at time of inspection of a 5 sty alt-1 at 4th fl,cmu wall in process. i observed a makeshift woof platform used to build a 2 tier supported scaffold

    Oct 11, 2017 · Penalty $500

    Resolve
  • Class - 1

    Sec. 3301.1.1 resposibility for safety. at time of inspection of a alt-1 in progress. i observed that there was accessible location at exp#34th sty level,there was no control access zone provided for safety mea

    Oct 11, 2017 · Penalty $1,600

    Resolve
  • Class - 1

    No guardrails. at time of inspection of a 5th sty alt-1 working on 4thfl cmu,i observed that guardrails at the elevator shaft locations wereinadequate at 2nd fl & 5th fl. also guardrails at 4th fl working deck

    Oct 11, 2017 · Penalty $1,200

    Resolve
  • Class - 2

    Failure to post permits at job site fence. at time of inspection of a 5 sty alt-1 at 4th fl. i did not observe any permits or project info panel at job site fence or exterior of job. remedy: post permits on pro

    Oct 11, 2017 · Penalty $400

    Resolve
  • Class - 2

    Project information panel. at time of inspection of a 5 sty alt-1 i observed no project information panel at 61-63 crosby street. remedy: comply w/code. provide project information panel.

    Oct 11, 2017 · Penalty $400

    Resolve
  • Non-hazardous

    Work w/o a permit at 4th floor metal ornamental cornice has been repaired and protions replaced andis still in progress suspended scaffolds are in place remedy stop al work obtain permit

    Aug 6, 1993 · Penalty $350

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

DatePriceTypeUnits
Jan 8, 2026$53,000,000Office buildings6

Building details

Building type
Office building (O5)
Year built
1900
Floors
5
Residential units
—
Building area
27,930 ft²
Lot area
5,429 ft²
Zoning
M1-5/R7D
Community board
102
Council district
1
Block / lot
482 / 13
Assessed value
$3,749,850
Landmark / historic district
SoHo-Cast Iron Historic District Extension

HPD registration #140285, last renewed Aug 26, 2019.

Questions about 63 Crosby Street

Who owns 63 Crosby Street?

The owner of record in NYC Department of City Planning PLUTO data is 61 Crosby Owner LLC.

Does 63 Crosby Street have violations?

Yes. NYC HPD has recorded 4 housing violations at this property.

Is 63 Crosby Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 63 Crosby Street built?

City records list 1900 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.