79 Eldridge Street
Manhattan, NY 10002BBL 1-00306-0029Map
Owner of record: Eldridge Hotel LLC
79 Eldridge Street is a hotel built in 2018 in Manhattan, 10002. The owner of record is Eldridge Hotel LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 2
- ECB violations
- 47
- HPD complaints
- 1
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 2
- Construction other optional
Borough commissioner stop work order application #122826843 due to contractor withdrawal. construction site is closed and padlocked, unable to determine percentage of work completed.
Oct 29, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 31, 2021
Dob violation - dismissed
ECB violations · 47
- Class - 2
At time of my inspection, i observed that information project panel was not eligble.comply with code
Nov 21, 2024 · Penalty $1,250
Resolve - Class - 2
Observed 14 story nb with no sidewalk shed at exp#1 where required-uppon checking site safety plan it shows shed should be in place(pedestrian protection) and installed at exp#1(not in place)-uppon checking dob
Jul 11, 2024 · Penalty $1,250
Resolve - Class - 2
Work without a permit expired permit.note:observed construction fence was installed without a valid permit.the previous permit#122826843-01-eq-fn expired on 09-15-2022.recurring condition;previously mentioned o
Apr 5, 2024 · Penalty $3,125
Resolve - Class - 2
Temporary construction equipment or installation on site expired permit #1228268243-01-eq-fn expired on 09-15-2022. remedy: renew permit.
Dec 26, 2023 · Penalty $1,250
Resolve - Class - 2
Temporary construction equipment or installation on site expired permit. #122826843-01-e9-fn expired on 09-15-2022. remedy: renew permit
Aug 29, 2023 · Penalty $1,250
Resolve - Class - 2
Observed 14 str new bldg- topped off, with a sidewalk shed at exp#1. the required red light marking the location of the standpipe connection was not provided on the outside/street-facing side of the sws, as req
Aug 28, 2023
Resolve - Class - 2
Observed a sidewalk shed at exp#1 with a loose/warped parapet panel, creating a hazard for pedestrians and/or vehicles. also observed vandalized markings on several parapet panels.
Aug 28, 2023 · Penalty $2,400
Resolve - Class - 2
Observed a jobsite fence at exp#1 not fully painted hunter green due excessive vandalized markings throughout, and with the viewing panel also partially painted, making it not fully see-through.
Aug 28, 2023 · Penalty $1,000
Resolve - Class - 2
Failure to maintain/display onsite documents required by bc chapter 33as noted at time of inspection on an active construction site,14 storynew building completed to bulkhead,observed at exp4 in place with new
Mar 2, 2023 · Penalty $625
Resolve - Class - 2
Temporary construction equipment onsite-construction plywood fence permit expired.as at time of inspection on an active construction site,observed construction plywood fence permit has expired on 9/15/2022 perm
Mar 2, 2023 · Penalty $3,125
Resolve
Show 37 more ↓
- Class - 1
Failure to notify dept of accident/incident that resulted in fatality or injury.note-worker was on aframe ladder lost balance&fell.worker suffering from pain in his back was taken to hosp.as per check of dept r
Jun 24, 2022
Resolve - Class - 2
Posting of unlawful signs information pictorial representation business or advertisting message on protective structures (fence) note:during time of inspection observed inactive job site graphitti on constructi
Nov 1, 2021 · Penalty $1,250
Resolve - Class - 1
Bc3301.6 failure to provide design drawings for platform.at time of inspection on active 14 story nb construction site observed platforms inside elevator shaft.when requested design drawings for platform was in
Aug 2, 2021 · Penalty $1,250
Resolve - Class - 1
Failure to maintain adequate guardrail as per code. at time of inspection on active 14 story nb construction site observed on 14th floor opening only maintain with sheetrock being used to close opening that ris
Aug 2, 2021 · Penalty $2,500
Resolve - Class - 2
Bc3314.4.8 failure to maintain pipe scaffold as per code.at time of inspection on active 14 story nb construction site observed pipe scaffold at exp #3 not maintained as per code pipe scaffold had inadequate ne
Aug 2, 2021
Resolve - Class - 2
Job site construction fence is not maintained.at time of inspection of a 14 story nb.observed job site closed with no construction activity.construction fence installed at exp #1 in poor condition and inadequat
Jun 2, 2021
Resolve - Class - 2
Bc3301.7 failure to provide approved pe details/eor noted:atoi for active const site@bulkhead level.observed:12"x12" opening (illegible) in all typical fl corridor slab&steel reinforcement rebar has been cut&re
May 14, 2021 · Penalty $1,250
Resolve - Class - 1
Bc 3301.7 failure to provide approved p.e design drawing. as noted:at time of inspection for an active construction site 14 stories. observed steel structure stairway installed up to roof level and concrete for
Jan 8, 2021 · Penalty $2,500
Resolve - Class - 2
Failure to maintain adequate housekeeping per section requirements. atthe time of inspection on an active job site currently at roof level,iobserved inadequate housekeeping,consisting of sheetrock,wood planks,m
Jan 4, 2021
Resolve - Class - 2
Bc 3314.8.2 debris netting. at the time of inspection on an active jobsite currently at roof level i observed debris netting around pipe scaffold at exposure 3 not properly enclosed to wall creating a potential
Jan 4, 2021
Resolve - Class - 2
Sec. 3301.2 safety measures & standars. atthe time of an inspection ofa new bldg under construction,i observed lots of 6-7" holes throughoutthe floor of a slab of a jobsite. improper holes creates penetration
Sep 1, 2020
Resolve - Class - 2
Sec. 3308.6 inadequate nettings. at the time of an inspection of a newbldg under construction,i observed inadequate nettings on the guardrails throughout the perimeter & at exp#1,exp#3 of the jobsite. vertical
Sep 1, 2020
Resolve - Class - 1
Failure to maintained records of prf-shift safety meeting for each worker.at the time of inspection i observe active jobsite with construction activities on-going ssc a.1(aporch present,upon request of prf-shif
Jun 29, 2020 · Penalty $2,500
Resolve - Class - 1
3307.4.3 udocks/barriers not filled/vehicular traffic.at the time of inspection i observe active jobsite with construction activities ongoing.at exposure#1 of proposed job barricade on die striet protecting & c
Jun 29, 2020 · Penalty $2,500
Resolve - Class - 2
Failure to safeguard/failure maintained safety operations.at the time of inspection i observe active construction jobsite.upon making walk through with designed ssc i observe various looking of caz(control acce
Jun 29, 2020 · Penalty $5,000
Resolve - Class - 1
Work contrary to stop work order at the time of my inspection responding to complaint#1538934,i observed hoist working against a stop work order that was posted 03-16-2020 violation#35469156m/57/y/58x work whil
Mar 17, 2020 · Penalty $5,000
Resolve - Class - 1
Bc330910-protectoin of roof/overhead.note:at the time of my inspectionof an active job site 14 story new building i observed missing roof protection for adj.property as exp#2-rear yard.also i observed inadequat
Mar 16, 2020 · Penalty $2,500
Resolve - Class - 1
Work does not conform to approved construction documents and or approved amendments.at the time of inspection i observed active constructionsite at 14 story new building.hoist at exp#1.temporary hoist as does n
Mar 16, 2020 · Penalty $625
Resolve - Class - 2
Work does not conform to approved construction documents and/or approved amendments.note:at the time of inspection i observed active construction.construction site at 14 story new building.also i observed tempo
Mar 16, 2020 · Penalty $625
Resolve - Class - 2
Bc 3301.2 failure to instittute/maintain safety measures @time of inspection of a 14 sty building under const i observed street/road enclosure equipment (yodocs) @exp.1 in the street.the yodocks were not filled
Nov 1, 2019
Resolve - Class - 2
Job site fence not constructed or maintained pursuant to subsection. @time of inspection of a 14 sty building under const, i observed a const fence with a gate,@exp.1 the gate was learning heavily & was crooked
Nov 1, 2019
Resolve - Class - 1
Bc33012-failure to institute/maintain safety measures.at time of inspection of a 14 story building under construction i observed that the top floor working deck had guard rails covered with plastic not allwed a
Nov 1, 2019 · Penalty $2,500
Resolve - Class - 1
Bc 3301.2 failure to maintain safety measures @time of inspection of aa 14 sty building under const, i observed that the sidewalk shed erected @xp.1 had a pipe/cross brace that partially blocked the fire escape
Nov 1, 2019 · Penalty $2,500
Resolve - Class - 1
28-301.1 failure to comply with dob high winds advisory. @time of inspection of a 14 sty building under const i observed that the horizontalnetting was left open (down) @exp.1+2 as per a dob weather advisory
Nov 1, 2019 · Penalty $2,500
Resolve - Class - 1
Bc 3307.6 sidewalk shed nnot constructed/maintained as required. @timeof inspection of a 14 sty new building under const, i observed a sidewalk shed with the following conditions:missing cross brakes. standpipe
Nov 1, 2019 · Penalty $625
Resolve - Class - 2
Bc33086-failure to or maintain horizontal safety netting where required.at time of inspection of a 14 story new building under construction i observed horizontal safety netting at exp 1 & 2,more than 2 stories
Nov 1, 2019
Resolve - Class - 1
Failure to perform to successfull hydrostattic pressure test of standpipe system. @time of inspection of a 14 sty new building under const, observed that the 10th floor had been pored. upon review of the dob
Nov 1, 2019 · Penalty $5,000
Resolve - Class - 1
Inadequate guardrails. at time of inspection i observed inadequate guardrails at the perimeter of the site at multiple levels. failure tocomply with osha regulations is a violation, and creates a hazard.
May 30, 2019 · Penalty $2,500
Resolve - Class - 2
Failure to safeguard all persons and property affected by constructionoperations. at time of inspection on an active construction site, notice that the sidewalls shed was built that in that it was obstructing
May 30, 2019 · Penalty $5,000
Resolve - Class - 1
3305.3.4 work not to approve drawings on construction site. at time of inspection on an active construction site 14 story new building, notice concrete formwork taking place on floors 6 and 7 a closer look at
May 30, 2019 · Penalty $2,500
Resolve - Class - 1
Gaps/holes/openings unprotected or inadequate protection at floors, multiple levels. at time of inspection i observed multiple holes/openings through floor slabs at multiple levels. this creates a possible fall
May 30, 2019 · Penalty $10,000
Resolve - Class - 1
Work not conforming to approve construction documetns. sidewalk shed. at time of inspection on an active construction site, notice that the sidewalk shed was not built according to what was on the approve plans
May 30, 2019 · Penalty $625
Resolve - Class - 1
Work not to site safety plan on site. at time of inspection on an active construction site, notice that dot approve barriers, pedestrianwalkway and partial sidewalk closure sign directions all were not in
May 30, 2019 · Penalty $1,250
Resolve - Class - 1
Housekeeping. at time of inspection i observed slip/trip hazards at the cellar, 1st, 4,5,6,and 7th floors. this is a failure to maintain housekeeping violation. rmdy: stop all new maintain housekeepig throug
May 30, 2019 · Penalty $2,500
Resolve - Class - 2
Failure to provide approved /accepted construction documents.at the time of inspection. at time of inspection it was observed that constractor failed to provide approved drawings for foundation and support.
Oct 10, 2018
Resolve - Class - 2
3307.3.2 failure to provide lot line fence. at the time of insepction observed no construction fence installed at exp#3 and exp#4 the contractor did not totally enclose his construction site and did not protect
Oct 10, 2018
Resolve - Class - 1
Sec. 3310.5.2 site safety not present. at time of inspection of a 14 sty bldg,currently on the foundation phase i observed 4 workers in the site conducting rebar installation. i requested to speak to the site
Jul 18, 2018 · Penalty $10,000
Resolve
Complaints
- Unsanitary condition
Pests
Sep 9, 2025 · Apt ROOM4D
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Hotel (H3)
- Year built
- 2018
- Floors
- 14
- Residential units
- —
- Building area
- 19,120 ft²
- Lot area
- 2,525 ft²
- Zoning
- C6-1G
- Community board
- 103
- Council district
- 1
- Block / lot
- 306 / 29
- Assessed value
- $2,994,300
- Landmark / historic district
- No
Questions about 79 Eldridge Street
Who owns 79 Eldridge Street?
The owner of record in NYC Department of City Planning PLUTO data is Eldridge Hotel LLC.
Does 79 Eldridge Street have violations?
NYC HPD has no housing violations on record for this property.
Is 79 Eldridge Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 79 Eldridge Street built?
City records list 2018 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.