roofy

50 Franklin Street

Manhattan, NY 10013BBL 1-00172-7504Map

Owner of record: 48-52 Franklin, LLC

50 Franklin Street is a condominium built in 2007 in Manhattan, 10013. It has 72 residential units across 18 floors. The owner of record is 48-52 Franklin, LLC. HPD has recorded 3 housing violations here, most recently on November 15, 2023.

HPD violations
3
DOB violations
15
ECB violations
38
HPD complaints
3

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Nov 15, 2023

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 3

  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 15, 2023

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 31, 2023

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 2, 2022

    Closed — Violation dismissed

DOB building violations · 15

  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 9, 2020

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 9, 2020

    Dob violation - resolved
  • Facade safety program facade required

    Fisp-facade safety program facade required

    Dec 6, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Aug 22, 2018

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Mar 10, 2017

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Mar 10, 2017

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Mar 2, 2016

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Mar 2, 2016

    Dob violation - resolved
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 15, 2014

    Dob violation - dismissed
  • Construction other optional

    Failure to maintain building

    Nov 3, 2013

    Dob violation - dismissed
Show 5 more ↓
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2011 inspection report

    Mar 1, 2013

    Dob violation - dismissed
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    Jan 1, 2012

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2010 inspection report

    Dec 13, 2011

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Nov 1, 2010

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Nov 1, 2010

    Dob violation - resolved

ECB violations · 38

  • Class - 2

    Pedestrian protection doesnt meet code spec atoi of replacement of balcony railings.contractor failed to install solid barrier in area of chute to protect pedestrian as per bc3307.6.4.4.also sws columns nearest

    Jul 15, 2021 · Penalty $625

    Resolve
  • Class - 2

    Work doesnt conform to const docs&approved.amendments.atoi of replacement of balcony railings,repair&concrete [email protected] observed pipescf frames@exp1 cut&modified approx6frames were cut&modified on top of

    Jul 15, 2021

    Resolve
  • Class - 2

    Fire extinguisher.noted:at time of inspection of an active jobsite,observed at roof level fire extinguisher missing tags and place of the ground.remedy:comply with nyc fire code.

    May 19, 2021

    Resolve
  • Class - 2

    Failure to maintain/display on site documents required by chapter 33.noted:at time of inspection of an active jobsite observed sidewalk shedin use and upon request to see sidewalk shed inspection report.observe

    May 19, 2021

    Resolve
  • Class - 1

    Failure to maintain bldg exterior walls/facades & appurtenances. north elevation exp#3: (@ eastside/corner)balconies: spalling concrete below decks- w/ 10th story exposing rebar, spalling conditions are also @

    May 18, 2018 · Penalty $2,500

    Resolve
  • Class - 2

    Sec. 3307.6.5.8 no periodic inspection observed. note: observed sidewalk shed in place no 6 months inspection on site as required by code specification. remedy: comply w/code.

    May 16, 2018

    Resolve
  • Class - 2

    Work does not conform to approved plans. note: at time of inspection observed sidewalk shed in place w/different height that is required by approved plans. also observed several columns out of plumb w/tolerance

    May 16, 2018 · Penalty $1,250

    Resolve
  • Class - 2

    Failure to provide parapet job sign panel. note: at time of inspectionobserved sidewalk shed in place w/o project information panel,sidewalkshed parapet panel construction sign not provided. remedy: comply w/co

    May 16, 2018

    Resolve
  • Class - 2

    Failure to file annual certifictation that cooling tower1000001315 hasbeen inspected,tested,and disinfected,and that a maintenance plan has been developed and implemented,by november 1,2016.rem:file annual cert

    Jun 20, 2017 · Penalty $1,000

    Resolve
  • Class - 2

    Uses not permitted.unless specifically permitted in 40.7,flexible cords and cables shall not be used for the following:1-as a substitute forthe fixed wiring of a structure dot. bsmt electrical room: used flexib

    Oct 24, 2013

    Resolve
Show 28 more ↓
  • Class - 1

    Failure to maintain bldg in a code compliant manner. noted:at south facing elevation(franklin st) 7th flr, 8'x5'pane of glass facade cracked and displaced.rmdy: make safe immediately-provide protection submit

    Jul 14, 2013 · Penalty $1,000

    Resolve
  • Class - 1

    Failure to safeguard all persons & property affected by construction operations noted: new building with c of o for flrs 1,2,3-11 had at least 10 fire stair doors held open destroying the integrity of the fire

    Aug 21, 2009 · Penalty $1,200

    Resolve
  • Class - 1

    Failure to have site safety manager or coordinator present as required-upon inspection construction of nb in progress. at time of inspection noted workers are working on various flr but the site safety manager

    Aug 17, 2009 · Penalty $2,400

    Resolve
  • Class - 1

    Sec 3307.8.1 toe board requirement noted from 3rd from to 17th fls north east & west of bldg missing toe boards at window openings rem: provide toe boards

    Mar 31, 2009 · Penalty $1,600

    Resolve
  • Class - 2

    Failure to safeguard all persons and property affected b construction operations observed recent refuse w/ construction site in violation of nyc fire code 1404.1 smoking refuse observed near 12th fl northwest e

    Mar 31, 2009 · Penalty $1,200

    Resolve
  • Class - 1

    Failure to safeguard all persons & property affected by construction operation. as noted: respond to an incident which took place at above active construction site. as reported by site safety manager during unl

    Mar 23, 2009 · Penalty $2,400

    Resolve
  • Class - 2

    Work w/o permit; expired permit noted: hoist permit #110091686-01-eq-ot has expired as of 2/21/09 for personal/material dual gage hoist. remedy: stop entire hoist renew permit call best squad for re-inspection

    Feb 23, 2009 · Penalty $400

    Resolve
  • Class - 1

    Sec. 3314.3.1.1. supported scaffold requirement design drawing provided is contrary to existing conditions - tie-in to bldg and type of scaffolding installed are both contrary to design drawings. scaffolding

    Feb 17, 2009 · Penalty $800

    Resolve
  • Class - 2

    Sec bc 3308.1.1 misc viol: fail to maintain vertical netting- observedvertical netting poorly maintained & some areas missing on upper floor12 to roof. remedy: maintain- fix replace vertical nets- on upper flrs

    Feb 2, 2009 · Penalty $800

    Resolve
  • Class - 2

    Sec bc 3313.1 misc viol: fail to comply w/nyc fire code. on insp several kerosine heaters on floors 13 to 9 all working & ignited. fire safety water has no fire safety log book. remedy: provide fire safety log

    Feb 2, 2009 · Penalty $800

    Resolve
  • Class - 2

    Failure to safeguard all persons and or property affected by construction operations upon inspection on active jobsite observed recent smoking refuse w/ construction site in violation of nyc fire code 14041 smo

    Jan 14, 2009 · Penalty $1,200

    Resolve
  • Class - 2

    Failure to safeguard all persons and/or property affected by construction operation. upon inspection on active job site observed recent smoking refuse w/i construction site in violation of nyc fire code 1404.1

    Nov 28, 2008 · Penalty $1,200

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping per sec requirements-upon inspection as observed large quantity of construction materials,debris,power cables for tools blocking walkway,tripping hazard.debris outisde

    Nov 3, 2008 · Penalty $800

    Resolve
  • Class - 2

    Failure to safeguard all persons & property affected by construction operation-upon inspection construction of nb is in progress.at time ofinspection observed smoking w/in construction site in violation of nyc

    Nov 3, 2008 · Penalty $1,200

    Resolve
  • Class - 1

    Failure to safeguard all persons and property affected by construction operation as noted at time of inspection at above const site const work in progress thruout the bldg observed workers were using adjacent

    Aug 19, 2008 · Penalty $2,400

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping per section requirements as noted at time of inspection at above location const work in progress thruout bldg excessive amount of debris (masonry lumber and rubbish)

    Aug 19, 2008 · Penalty $400

    Resolve
  • Class - 1

    Failure to provide protection on roofs roofs outlet and skylights of adjoining property as noted upon inspection at above location construction work at west elevation (brick work) in progress roof protection

    Aug 19, 2008 · Penalty $1,600

    Resolve
  • Class - 1

    Failure to institute maintain safety equipment measures or temp const no toe board upon inspection pipe scaffolding erected at the front and rear of the bldg under construction up to roof level at time of

    Aug 11, 2008

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping as per section requirements upon inspection construction of nb is in progress bldg at roof level at time of inspection as noted construction materials debris waste

    Aug 11, 2008 · Penalty $400

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping per section requirement. noted from 16th fl to 2nd fl there is debris, boxed, concrete, garbage t/o. remedy: maintain adequate housekeeping.

    Jul 1, 2008 · Penalty $800

    Resolve
  • Class - 1

    Failure to institute/maintain safety equipment measures or temporary construction - no toe boards noted: from 2nd to 18th floors both north & south sides toe boards are loose/missing or unsecured. remedy:

    Jul 1, 2008 · Penalty $1,000

    Resolve
  • Hazardous

    Opening/holes not coverd.-at time of inspection there are hole in the floor aprox 4 inx4in to 2ft x 3ft on floors 17 16 14,13,12,11,10,9,7,6and 2 causing a hazard. remedy: cover hole

    Jun 10, 2008

    Resolve
  • Hazardous

    Failure to safeguard public and property effected by construction operations at time of inspection on flrs 4 6 8-12 and 14 16 17 material is stored within 10ft of perimeter of bldg in some cases right up agains

    May 9, 2008 · Penalty $1,000

    Resolve
  • Hazardous

    Safety netting damaged or broken at time of inspection flrs 7-12 nets are loose cables are disconnected and inadequately maintained remedy: repair replace nets where needed maintain vertical safety netting as p

    May 9, 2008 · Penalty $1,250

    Resolve
  • Hazardous

    Sec.27-1009 failure to havesite saftey manager present as required at 4:05 on 5/9/08 there is no site safety manager present on site there are plumbers carpenters and laborers working on site i spoke to ray

    May 9, 2008 · Penalty $800

    Resolve
  • Hazardous

    Opening/flrs holes not covered. at time of inspection there are holes in flrs round holes apprx 8" and bigger and square holes 1'x1' and bigger on flr #5,6,7,8,9,10,11,12,13 mostly unsecured plywood overthem

    Apr 22, 2008 · Penalty $800

    Resolve
  • Hazardous

    Failure to provide adequate protection for sidewalk and walkways. at time of inspection no overhead protection is provided for walkways to enter building and on flr #12 set back. remedy: stop all work exterior

    Apr 22, 2008 · Penalty $800

    Resolve
  • Hazardous

    Failure to protect roofs. roof outlets, and skylights of adjoining property. note: work is in progress under application #104827797 w/o providing overhead protection for the adjacent property (west side) (expos

    Apr 7, 2008 · Penalty $500

    Resolve

Complaints

  • Nonconst

    Vermin

    Aug 17, 2012 · Apt 8C

    Close
  • Nonconst

    Vermin

    Aug 17, 2012 · Apt 8C

    Close
  • Heating

    Heat related

    Nov 10, 2010 · Apt PHB

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Condominium (RD)
Year built
2007
Floors
18
Residential units
72
Building area
73,624 ft²
Lot area
7,532 ft²
Zoning
C6-4A
Community board
101
Council district
1
Block / lot
172 / 7504
Assessed value
$15,836,760
Landmark / historic district
No

HPD registration #143245, last renewed Sep 24, 2025.

Questions about 50 Franklin Street

Who owns 50 Franklin Street?

The owner of record in NYC Department of City Planning PLUTO data is 48-52 Franklin, LLC.

Does 50 Franklin Street have violations?

Yes. NYC HPD has recorded 3 housing violations at this property.

Is 50 Franklin Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 50 Franklin Street built?

City records list 2007 as the year it was built.

How many apartments are in 50 Franklin Street?

It has 72 residential units and 155 units in total.